DESIGN, ENGINEERING, AND EXECUTION FOR THE CONDITIONING OF PHYSICAL SPACE OF THE DATA CENTER (WALLS, FALSE FLOORS, CEILINGS, SHORT FIRE BARRIERS, LIGHTING).
DESIGN, ENGINEERING, AND EXECUTION OF THE PRECISION COOLING SYSTEM, ENERGY SUPPORT, FIRE DETECTION SYSTEM, ACCESS CONTROL, AND TELECOMMUNICATIONS INFRASTRUCTURE FOR THE DATA CENTER.
WHAT WERE THE CHALLENGES?
- Finish a great project in a short time of implementation.
- A High density of telecommunications points.
- Many workers from different disciplines worked at the same time.
HOW DID WE SOLVE THEM?
- Appropriate human resources, materials, tools, and logistics were allocated.
- Appropriate engineering was carried out for route and space distribution considering ANSI / TIA / EIA standards.
- Activities were coordinated with the general supervision of work.
WHAT HELPED TO BE A SUCCESSFUL PROJECT?
- Organize the work of the various integrators of the different disciplines.
- Great work of the facilities team.