Comisión Nacional Bancaria y de Valores
Success story at Data Center
Address: CDMX, México
Period: July 2019 – January 2020
IMPLEMENTATION OF THE BMS MONITORING SYSTEM IN THE DATA CENTER.
IMPLEMENTATION OF THE DCIM MONITORING SYSTEM IN DATA CENTER.
IMPLEMENTATION OF THE ACCESS CONTROL SYSTEM.
WHAT WERE THE CHALLENGES?
- Criticality of items as it is an active Data Center.
- Decisive project for the financial client, with high technical specification.
- Interaction with other suppliers, at the time of running the project.
HOW DID WE SOLVE THEM?
- Coordinated work with the client, to determine the opportunity for implementation.
- Experience in a similar project.
- Planning activities with the general supervisor of work.
WHAT HELPED TO BE A SUCCESSFUL PROJECT?
- Total customer availability and opening to intervene during the operation of the Data Center.
Category: Data Center